DATA CENTRE CONSTRUCTION


Project Description

In partnership with our client we carried out the complete construction of a new 140sq.mtr data hall complete with main HV electrical supply, UPS derived supply and onsite LV power generation via a 500KVA Generator. We completed the design in 4 weeks and carried out the complete construction which included:-data hall construction, switch-room construction, main electrical infrastructure, mechanical cooling to data hall, UPS power cabling and infrastructure, Generator installation & cabling and the complete FAT, SAT and IST testing for handover to client.

GROUP SERVICE:

TPL - CRITICAL

CLIENT:

Confidential

LOCATION:

London

PROJECT COST:

£1.2million

DESIGN PHASE - 4 weeks
100%
CONSTRUCTION PHASE - 20 weeks
100%

We are happy to provide references relating to any of our projects however given the confidential nature of all our clients we cannot publish all details of the installation works on this public website.