DATA HALL REFURBISHMENT


Project Description

We were instructed to carry out the segregation of one data hall space into two separate data halls to enable our client to sublet the space. The works included construction of a new security wall between the live data halls, relocation of electrical and mechanical plant, reconfiguring of fire alarm and suppression system and re-routing of critical live mechanical and electrical services. The planning and implementation of these works meant that no services were lost during the construction works within a live critical environment.

GROUP SERVICE:

TPL - PROJECTS

CLIENT:

Confidential

LOCATION:

London

PROJECT COST:

£280,000

PLANNING PHASE - 4 weeks
100%
CONSTRUCTION PHASE – 12 weeks
100%

We are happy to provide references relating to any of our projects however given the confidential nature of all our clients we cannot publish all details of the installation works on this public website.